Monday, March 4, 2013

POST 16- Plumbing prep, trailblazing, and a fairly accurate layout


Ok, so my concrete guy didn't show up today (again), and it would have been a great day to start.  Weather has been a factor, but I have people coming up in 7 days to frame.  I'm getting a little bit antsy, it's crunch time: I have to have the form up and rebar/steel in it, get inspected, and then pour and finish the concrete by next Monday...if I don't at least get the form up and inspected by friday afternoon (4 business days from now!) I'm hosed.

I went ahead and did the plumbing stubouts, I've got the pvc cut and together, and just waiting for my form to go up so I can slip it in there.


Just waiting on my concrete guy....



Here's a before and after pic from when Josh and I blazed a trail the other day...




Before











                                                     After-->









And here's a (moderately) accurate actual layout of the house...









<--spray can is location of toilet stubout, cap is shower drain

















More to come later, I'm waiting on a call back from my concrete guy.